NO VALID NOR = NO DEMURRAGE
In Trans Trade v Sebat Shipping a vessel was fixed to carry barley from Constanta to Brake. The cargo was fumigated on completion of loading. On opening the hatches at Brake phosphene levels in the holds were determined to be too high to permit the vessel to discharge and it was sent to the anchorage for 74 days.
The arbitration Tribunal found that since NOR was tendered at Brake before dropping anchor that the vessel was not then an arrived ship and they found that laytime commenced by default when the hatches were first opened.
Charterers obtained leave to appeal on the question of whether in the absence of valid NOR without any agreement, waiver or estoppel laytime ran at all.
Although the Tribunal declared that in their opinion it was “trite law” that, absent valid NOR, time ran from commencement of cargo operations the Court found this to be a clear error of law by the Tribunal: see the Mexico I (1990). In the absence of valid NOR time does not count unless there is agreement, waiver or estoppel.
Owners – if in doubt as to the validity of NOR keep tendering NOR regularly throughout stays in port.
FAILURE TO PROVIDE REFUND GUARANTEES NOT A BREACH OF CONDITION
In SLB v PAK each of 10 Claimants entered into materially identical shipbuilding contracts with the Defendant subsidiaries of a shipyard for the purchase of container vessels of either 12,690 or 15,000 TEUs. Payment was to be in installments prior to and upon delivery and the Buyers were entitled to a refund of any amount paid before delivery upon termination by the Buyers in accordance with the terms of the contracts. The Sellers were to provide Refund Guarantees issued by certain Chinese banks in respect of any amounts paid prior to delivery.
Article X(A) of the contracts set out various events which would be considered a default by the Seller included in which was the following provision at Article X(A)(f):
“The [Refund Guarantee] is not delivered to the BUYER in accordance with the terms of this CONTRACT by no later than 120 days after the date this CONTRACT is amended, novated and restated or such later date as the BUYER may designate in writing from time to time, then and in any such case the BUYER may terminate, rescind or cancel this CONTRACT by notice to the SELLER in writing or by telefax confirming in writing in accordance with the provisions of Article X hereof.”
The Sellers failed to provide the Refund Guarantees within 120 days of the novation of the contracts. The Buyers cancelled the contracts and claimed in London arbitration loss of bargain damages amounting to between USD 73 million and USD 83 million for loss of profit and the costs of purchasing substitute vessels.
The principal issues to be determined by the Tribunal were whether:
(i) Article X(A)(f) was a condition of the contract, thereby entitling the Buyers to damages, or otherwise only an innominate term;
(ii) If Article X(A)(f) was an innominate term, whether the Sellers evinced an intention not to perform the contracts so to amount to a repudiation entitling the Buyers to damages.
The Tribunal determined Article X(A)(f) was an innominate term and that the Sellers were not in repudiatory breach and the Buyers’ claim for damages therefore failed. The Buyers were granted permission to appeal under Section 69 of the Arbitration Act for error of law on the question of whether Article X(A)(f) was a condition.
Calver J applied the relevant legal principles derived from the authorities as follows:
(i) Although the words “by no later than 120 days” were in principle capable of giving rise to a condition, they did not necessarily do so and the fact that the 120 day requirement was qualified by an option for the Buyer to designate a later date pointed away from the conclusion Article X(A)(f) was a condition.
(ii) The Judge rejected the Buyers’ argument that the obligation to provide a Refund Guarantee was interdependent with the payment obligations upon the Buyers so that the delivery of the vessels required X(A)(f) to be a condition. The Judge found that the absence of a condition would not cause the contracts to fall into unworkable disarray since there were provisions which dealt with delay for delivery.
(iii) The Judge held that it was both inconsistent and unattractive for a right to terminate the contracts and claim damages for delay when there were comprehensive contractual remedies dealing with delay and a right of the Buyer to extend time or rescind the contract with the stated effect that all obligations under the contract would be discharged.
(iv) The need to promote certainty in a commercial contract must be balanced against the undesirability of disproportionate outcomes for technical breaches. Article X(A)(f) bore the hallmarks of an innominate term given that the consequences of a breach might or might not be serious.
(v) The Buyers were not required to make any payments without a Refund Guarantee having been provided. Calver J agreed with the Tribunal’s reliance on the “Hansa Murcia” [2013] for the proposition that a breach of a provision to provide a Refund Guarantee would not go to the root of the contract unless the buyer was exposed to a real practical risk of losing the payments which were to be secured.
In light of these findings Calver J determined Article X(A)(f) was an innominate term and the Buyers were not entitled to damages if they cancelled the contracts pursuant to its terms.
PERFORMANCE CLAIM – EXTERNAL DATA USED IN ABSENCE OF LOG BOOKS
In a recent London Arbitration, a vessel was chartered for a trip time charter on an amended NYPE 1946 form.
The recap contained the following performance warranty:
ABOVE SPEED AND CONSUMPTION ARE GIVEN IN CONTINUE 24 HOURS GOOD WEATHER / SMOOTH SEAS AND UNDERSTOOD TO MEAN ALL WEATHER CONDITIONS NOT EXCEEDING BEAUFORT SCALE FORCE 4 (MAX 16 KNOTS), AND TOTAL COMBINED (SEA AND SWELL) SIGNIFICANT WAVE HEIGHT CONFINED TO LIMITS OF DOUGLAS SEA STATE 3 (0.5M – 1.25M) WITH NO ADVERSE CURRENTS AND NO NEGATIVE INFLUENCE OF SWELLS. NO EXTRAPOLATIONS TO BE MADE FOR WEATHER CONDITIONS OTHER THAN THOSE DESCRIBED ABOVE.
Rider clause 79 provided:
The charterers may supply an independent weather bureau… Evidence of weather conditions shall be taken from the vessel’s deck logs and independent weather bureau reports. In the event of consistent discrepancy between the deck logs and the independent weather bureau reports, a third mutually agreed independent weather routing company to be appointed, whose report to be taken as final and binding.
It was common ground that the Charterparty defined good weather as follows:
Wind speed must not exceed Beaufort 4.
Sea state must not exceed 1.25 metres.
No adverse currents.
The above conditions must apply at least 24 continuous hours.
Charterers’ weather routing company (WRC) found such a period. It had identified a period of 47 continuous hours of good weather. During that period, the WRC assessed the vessel only achieved 12.26 knots against a target speed of about 14 knots.
Owners argued that the WRC good weather period was not a good weather period. They said that the WRC had failed to properly consider the impact of swell given the provision “no negative influence of swells” and had not made proper deductions for the effect of current. Owners maintained the WRC had failed to request the vessel’s log books or take the log books into consideration in assessing performance.
There was also the issue as to the meaning of the provision “NO EXTRAPOLATIONS TO BE MADE FOR WEATHER CONDITIONS OTHER THAN THOSE DESCRIBED ABOVE”. Owners argued this amounted to a prohibition on extrapolating good weather underperformance across periods which were not themselves good weather periods. Charterers argued the provision simply prohibited extrapolation of underperformance from periods which were not properly good weather periods, while permitting extrapolation from periods which were properly good weather periods. Charterers cited Lloyd LJ in the Gas Enterprise [1993] in which he held that “very clear words” would be required to prohibit extrapolation of good weather underperformance across a voyage.
The Tribunal criticised the parties for failing to jointly appoint a third-party weather bureau to determine underperformance in accordance with the clause 79 dispute resolution mechanism, which may have saved the parties the time and cost of the present proceedings. Owners were criticised for failing to adduce the vessel’s log books and then seeking to criticise the WRC for not taking the logbooks into consideration. Charterers’ WRC weather data was found to have been appropriately sourced and its methodology was appropriate. It had properly accounted for the negative influence of swell and the impact of current.
Charterers had prima facie satisfied the burden of establishing underperformance. The absence of the log books or the appointment of a third-party WRC under clause 79 to resolve the dispute meant that Owners had failed to overcome Charterers’ prima facie case. Moreover, the Tribunal was satisfied that a propeller slip factor of 25% during the good weather period clearly denoted underperformance.
As to extrapolation, the Tribunal was satisfied that Charterers’ interpretation was correct. Extrapolation of good weather underperformance across the entire voyage had not been excluded by the parties. Clearer words were required to have such an effect.
Charterers’ claim therefore succeeded in full.
CHINA TIGHTENS ITS GRIP ON CARRIAGE OF GOODS BY SEA
A revised Chinese Maritime Code came into effect on 1 May 2026.
Key amendments and implications include:
- Chinese maritime law will apply compulsorily to contracts of carriage, overriding any foreign governing law clauses, if either the port of loading or discharge is in China. Bills of Lading, Charterparties and other contractual arrangements will be affected as a result.
- Both international and domestic coastal carriage of goods by sea are now governed by the Code. Stricter liability standards are imposed on domestic coastal carriage including but not limited to a continuous obligation of seaworthiness throughout the voyage and potential liability for delays in delivery even where no delivery time is explicitly agreed.
- The definition of actual carrier is expanded to include parties entrusted/contracted, or sub-contracted, by the carrier who actually perform all or part of the carrier’s cargo-handling obligations resulting in a broad group of participants benefiting from established protections applying to carriers. Terminal operators may be treated as actual carriers.
- The responsibility of the carrier has been expanded to include receipt and delivery of cargo.
- Subject to certain limitations, the carrier may now exercise a possessory lien over goods even where such cargo is not owned by the debtor, provided there is a sufficient connection between the cargo and the underlying claim.
- A more flexible limitation period regime is introduced. The one-year limitation period can now be interrupted by demands for performance, commencement of proceedings or an acknowledgment of liability. A six-year long-stop limitation period running from the end of the common maritime adventure applies to General Average claims and recourse claims from cargo disputes may receive a new 90-day period if less than 90 days remain in the original one-year limitation period after settlement.
- Unless otherwise agreed, the transfer of mortgaged ships can now be effected without the mortgagee’s consent. The mortgage remains attached to the ship after the transfer.
- Electronic transport documents are expressly recognised as having full legal effect.
- A new regime is established for ship-source oil pollution damage.
DETENTION DAMAGES UNDER VOYWAR WHILE AWAITING CHARTERERS’ ORDERS
A vessel was fixed on the Gencon 1994 form for a voyage carrying ammonium nitrate from a loadport in the Azov Sea for discharge at a port in the Black Sea.
Clause 17 of the charter was the BIMCO Voywar 1993 clause which provided at subclause (c) that “Owners shall not be required… to proceed or continue on any voyage, or on any part thereof… where it appears… at any stage of the voyage [after loading] that, in the reasonable judgement of the Master and/or the Owners, the Vessel… may be, or are likely to be, exposed to War Risks. If it should so appear, the Owners may by notice request the Charterers to nominate a safe port for the discharge… and if within 48 hours of the receipt of such notice, the Charterers shall not have nominated such a port, the Owners may discharge the cargo at any safe port of their choice (including the port of loading) in complete fulfilment of the Contract of Carriage. The Owners shall be entitled to recover from Charterers the extra expenses of such discharge….”
Performance of the contractual voyage required transit through the Kerch Strait and under its eponymous bridge. However, when the laden vessel arrived there on 15 January 2023 she was forbidden by the Russian authorities to proceed. It transpired this was because she was laden with ammonium nitrate which although a fertiliser is potentially usable in explosives (cf the Baltic Exchange bomb in 1992).
Owners succeeded with their claim for detention damages at the contractual demurrage rate from 15 February 2023 when they requested new voyage orders of Charterers pursuant to the Voywar clause until 15 March when those orders were given by Charterers.
The availability of detention damages under Voywar, in both the 1993 and subsequent 2013/2025 revisions, which are not materially changed for present purposes, should Charterers fail to issue alternative orders when called on to do so will be welcome news to Owners. So too will the Tribunal’s apparently wide approach to the “change in the nature… or… degree sufficient to make [the risk] qualitatively different” from that at the time of the charter required to rely on Voywar after the Supreme Court decision in the “Polar”.
NO RIGHT TO REJECT NOMINATION AND TERMINATE
Disputes arose out of a contract for the sale of petrochemical products made between the seller, FinCo, and the buyer, Integra, under an email recap incorporating BP’s Oil International Limited General Terms and Conditions for Sales and Purchases of Crude Oil and Petroleum Products, the “BP GTCs”, and Incoterms 2010.
FINCO purported to terminate the contract whilst the loaded vessel was nearing the disport and claimed for the US$2.6 million balance of the price paid to Integra. The Court had to decide whether FINCO was entitled to reject a substitute vessel nomination and terminate the contract on either of two claimed grounds.
(i) The contract had originally provided for delivery ex ship (“DES”) between “delivery dates: 10-24 November 2023” but was varied to be on CIF terms. It was common ground that the late arrival of the vessel on 27 November 2023 would, had the contract remained on DES terms, have been a breach of contract justifying termination.
The Court held that the same did not hold true after the amendment, rejecting Integra’s argument that under CIF terms the cargo was in fact delivered early when loaded on 24 October 2023 but accepting its alternative position that s.11.3 of the BP GTCs rendered the delivery dates “indicative only”, obliging Integra only to ensure the vessel tendered NOR at the loading terminal at a time consistent with the agreed indicative arrival date at Amsterdam*. There was no breach and FinCo was not entitled to terminate.
(ii) FinCo said that the performing vessel nominated by Integra was too large for the discharge terminal. It said that it had validly rejected its nomination and that Integra’s failure to nominate an alternative was a renunciatory or repudiatory breach. The BP GTCs provided to material effect that the buyer should “give notice accepting or rejecting any Vessel nominated by the seller within 1 Business Day” of that nomination (s.14.6.1), and that “the Buyer shall have the right (which right may only be exercised prior to the passing of property hereunder) to refuse, on any reasonable grounds, to accept” the nominated vessel (s.14.6.2).
Whilst FinCo contended that it had rejected the Vessel the business day after Integra’s nomination, the Court had no difficulty in finding that it had not done so by the contractual medium or with sufficient certainty.
In circumstances where FinCo had given contractual notice only on 9 October, two working days after nomination, the next question was: Did ss.14.6.1 and 14.6.2 establish two independent rights of rejection, one with the “1 Business Day” limit and the other without?
Having regard to the importance of promptness in accepting or rejecting a nomination generally, to the absence of a reason why the parties should have intended to create independent but overlapping rights of rejection, and to the provision of s.14.6.3 allowing for rejection outside the time limit where something new subsequently emerged, the Court held that ss.14.6.1 and 14.6.2 were two parts of a single right: the former setting out how the right was to be exercised, and the latter developing the specifics of that right.
Even had ss.14.6.1 and 14.6.2 provided for separate rights of rejection, the Court concluded obiter that in later communications FinCo had estopped itself from asserting that Integra had breached its nomination obligation by proceeding on an alternative plan to discharge and tranship by barges. Integra was not in breach of the contract and FinCo had no right to terminate.
WHAT CAN HAPPEN IF YOU DON’T PAY HIRE
In a dispute referred to London arbitration under full LMAA Terms, Owners claimed unpaid hire and other sums totalling USD 1,952,549.63 while Charterers counterclaimed the total amount of USD 3,749,500 in respect of, among other things, losses arising out of the Owners’ alleged wrongful arrest of another vessel.
The Tribunal’s first decision was a Partial Final Award in respect of the Owners’ application for unpaid hire which they argued was indisputably due and owing. The Charterers asserted that while an amount was due to the Owners in respect of hire, they were entitled to set it off against their counterclaim.
However, the Charterers accepted they were unable to plead a case of wrongful arrest due to the absence of malice or gross negligence which led the Tribunal to conclude that Charterers had no entitlement to set off as they contended.
Charterers were ordered to pay Owners the minimum sum of USD 699,989.11 together with interest at a rate of 7%. Charterers were also ordered to pay the Owners’ costs of the application and the costs of the Partial Final Award together with interest on those costs.
A second Partial Final Award followed whereby on 16 January the Tribunal ordered Charterers to provide security for the Owners’ costs in defending the Charterers’ counterclaim in the amount of £20,000 to be provided no later than 7 February.
Although the Charterers proposed to provide the security by way of a solicitor’s undertaking, security was not provided and on 5 March the Owners applied for a Peremptory Order that the Charterers provide security within 8 March. The Tribunal stated that a Peremptory Order requiring compliance by 12 March would be made unless it could be persuaded not to make such an Order within the following day. Upon Charterers’ request, on 9 March the Tribunal extended the deadline for compliance with the Peremptory Order to 15 March.
Upon security not being provided as ordered, the Tribunal dismissed the Charterers’ counterclaim in its entirety for their failure to comply with a Peremptory Order for security for costs pursuant to Section 41(6) of the Arbitration Act 1996. The Charterers were also ordered to pay the Owners’ costs relating to the Charterers’ counterclaim and the costs of the Partial Final Award together with interest on those costs.